Since 2018, CVE has had the opportunity to be an electrical trade partner for DataBank’s Granite Point Campus construction projects. The 23-acre site includes four Tier II data centers (DataBank SLC 2, 3, 4, 5) and a 66 megawatt (MW) substation constructed by CVE’s Transmission Line & Substation team. Currently, CVE is working with Layton Construction on the construction of SLC6—DataBank’s new 32 MW 211,000 square foot Tier II data center.
DATABANK SLC5
Over 24 months, CVE provided automatic static switching equipment for a new 100,000 square foot facility. CVE successfully constructed the full electrical buildout of 6 UPS rooms including UPSs, medium voltage transformers and 3000 kW generators, house electrical system, two data halls and two-story office area. Scope of work included:
DATABANK SLC4
CVE coordinated and executed (3) redistribution outages on existing feeder in a live data center with a 2 MW power adder and annexed a “C” block to two data halls. Scope of work included:
DATABANK SLC3
CVE coordinated and executed (3) redistribution outages on existing feeder in a live 425,000 foot data center with a 2 MW power adder and annexed a “C” block to two data halls. Scope of work included:
DATABANK SLC2
CVE coordinated and executed (4) redistribution outages on existing feeder in a live data center with a 2 MW power adder and annexed a “C” block to one data hall. Scope of work included:
> Installation of (2) 1,000 kW UPSs, (8) PDUs. and (16) RPPs to an existing facility